General
Electric v. GRDA & Benham Holway
– on behalf of Defendant, calculated total construction costs
incurred by Plaintiff. Plaintiff was claiming $20,000,000 in
additional cost and delay damages. Provided a total cost
report. Case settled favorable to Defendant.
Crawford Tire
Company v. Transamerica Ins – retained by the Defendant.
A suit for bad faith stemmed from a contract surety matter. The
Plaintiff claimed that Defendant did not process surety claims
properly or in a timely manner. Report prepared - Deposition
given. The client settled favorably and paid for only invoices
that were determined to be timely and proper.
Duvall
Construction v. Brookfield Lowry – retained by the
Defendant. The Defendant was the general contractor for an
elementary school facility and the Plaintiff was a subcontractor
providing heavy equipment and labor to install sewer and water
lines to the building. Engaged to review and critique the
Plaintiff's alleged claims against Defendant. Report was issued
resulting in a favorable settlement for Defendant.
Flintridge
Development v. Benham Holway – on behalf of Defendant
rebutted alleged damages calculations as produced by Plaintiff's
expert relative to services in an errors and omissions claim.
After reviewing and issuing a report concerning the Plaintiff’s
alleged increased cost and claims of decreased sales price for
residential lots a favorable settlement was reached for the
Defendant.
The Garney
Company v. The City of Tulsa et al. – on behalf of
Defendant, provided financial analysis relative to errors and
omissions claim. Reviewed documents and issued a verbal report
of damages prior to mediation. The claim was favorably settled
at mediation.
Protein and
Fat Technology v. Seaboard Farms Oklahoma – on behalf of
Plaintiff, prepared a total cost claim for work performed in
providing and installing equipment in a processing plant. The
majority of the claims were due to the owner providing a
building 18 inches shorter than agreed. All issues were settled
prior to the mandatory arbitration, except for damages caused by
the reduction in ceiling height. Written report was issued.
Suit was arbitrated; findings are confidential.
Manor Downs v.
WAG Construction – on behalf of Plaintiff, determined if
Defendant had properly billed Plaintiff in accordance with cost
plus contract. Calculated billings under the contract and
provided written report. Plaintiff received favorable
settlement.
CCC v.
Caterpillar – on behalf of Plaintiff collected pertinent
data and calculated damages resulting from delays relative to the
construction of a diesel powered power plant in Nicaragua.
Prepared display schedules and graphics for presentation to
arbitrator. Arbitrated favorable award to Plaintiff.
Church L. P. v. CDH Construction v Third Party Defendant,
TDI -
on behalf of Defendant, rebutted Plaintiff's allegations
regarding damages caused by delay, loss of market price, etc for
the late completion of a privately owned residential dorm
located in College Station. Reviewed documents and prepared
schedules and graphics for use by attorneys at arbitration.
Arbitrated to a satisfactory conclusion for Defendant.